Amended BharatNet Program (ABP)
Gram Panchayats Upgraded
12,023 as on 31 May-26
↑ 1,721 in May-26
🏘️
OFC Laid (KM)
38,939 as on 31 May-26
↑ 5,319 in May-26
🔌
Net FTTH Connections
1,91,986 as on 30 April-26
↑ 21,840 in April-26
📡
Monthly Data Consumption (TB)
2,02,076 April-26
↑ 16,126 in April-26
📊
Gram Panchayats upgraded (Mar-26 to May-26)
12,023
OFC Laid in Km (Mar-26 to May-26)
38,939 km
Net FTTH Connections (Feb-26 to Apr-26)
1,91,986
Monthly Data Consumption in TB (Feb-26 to Apr-26)
2,02,076 TB
📶
Mobile Tower
Total Towers Commissioned
24,338 as on 30 April-26
↑ 87 in April-26
🗼
Total Villages Covered
34,188 as on 30 April-26
↑ 127 in April-26
🏡
Towers Commissioned
24,338
Villages Covered
34,188
🌊
Submarine OFC
🏝️
Chennai – A&N Island Project
 
Project Cost: INR 1,224 Cr
8 Islands
Connected
2,312 Cable Laid
(km)
Project Completion100%
Kochi – Lakshadweep (KLI) Project
 
Project Cost: INR 1,072 Cr
11 Islands
Connected
1,869 Cable Laid
(km)
Project Completion100%