Amended BharatNet Program (ABP)
Gram Panchayats Upgraded
23,414 as on 31 Jul-26
↑ 9,920 in Jul-26
🏘️
OFC Laid (KM)
49,439 as on 31 Jul-26
↑ 5,532 in Jul-26
🔌
Net FTTH Connections
2,61,995 as on 31 Jul-26
↑ 20,196 in Jul-26
📡
Monthly Data Consumption (TB)
2,11,093 Jun-26
↑ 1,783 in Jun-26
📊
Gram Panchayats upgraded (May-26 to Jul-26)
23,414
OFC Laid in Km (May-26 to Jul-26)
49,439 km
Net FTTH Connections (May-26 to Jul-26)
2,61,995
Monthly Data Consumption in TB (Apr-26 to Jun-26)
2,11,093 TB
📶
Mobile Tower
Total Towers Commissioned
24,784 as on 30 Jun-26
↑ 298 in Jun-26
🗼
Total Villages Covered
35,022 as on 30 Jun-26
↑ 616 in Jun-26
🏡
Towers Commissioned
24,784
Villages Covered
35,022
🌊
Submarine OFC
🏝️
Chennai – A&N Island Project
 
Project Cost: INR 1,224 Cr
8 Islands
Connected
2,312 Cable Laid
(km)
Project Completion100%
Kochi – Lakshadweep (KLI) Project
 
Project Cost: INR 1,072 Cr
11 Islands
Connected
1,869 Cable Laid
(km)
Project Completion100%