1- As of 31.05.2026, 4,718 villages have been connected by installing 3,054 mobile towers in Andhra Pradesh, Chhattisgarh, Jharkhand, Odisha and Maharashtra.
2- Further, 41 villages of Chhattisgarh has also been included under the project on the recommendation of MHA against the deleted villages/locations and letter issued to M/s RJIL vide dated 15-01-2026 having roll out period of 1 year i.e. upto 14-01-2027. As 31.05.2026, survey has been completed and 40 towers have been planned for covering 41 villages. Installation work is under progress.
| No. of Order | Executable scope after survey | Towers Commissioned | Villages Covered | |
|---|---|---|---|---|
| Villages | Towers | |||
| May 2022 order | 5531 | 3722 | 3054 | 4718 |
| January 2026 Order | 41 | 40 | 0 | 0 |
| Total | 5572 | 3762 | 3054 | 4718 |