The agreement was signed with M/s Bharti Hexacom Limited (M/s BHL) on 04.09.2020. The project envisages 4G-based mobile coverage by installing 878 mobile towers in 1164 uncovered villages and 11 mobile towers along national highways at a cost of Rs 726.65 crore.

Status so far

Physical survey of the sites by M/s Bharti Hexacom Limited (M/s BHL) is completed and the installation is in progress. As on 04.08.2022, 284 BTS (Base Transceiver Station) have been installed and commissioned, covering 425 villages. The target for completion of this project is September 2022.