TARGETS AND GOALS SETTING FOR THE FY YEAR 2022-23
Sl. No. | Goals | Target Q1 | Target Q2 | Target Q3 | Target Q4 |
---|---|---|---|---|---|
1 |
Provision of submarine Optical Fibre Connectivity between Kochi and Lakshadweep islands (KLI Project) |
Approval of EIA/CRZ, Wildlife clearance etc. report by MoEF&CC |
Equipment/Submarine Plant Manufacturing & Factory Acceptance Testing(FAT) |
Cable loading and Equipment Transport. |
-Submarine Cable laying and Testing. -Land Cable Installation -Equipment Installation |
2 |
Provision of 4G mobile Services in 85 Uncovered villages and seamless mobile coverage along NH-4 in Andaman & Nicobar Islands. |
No. of Tower Sites to be installed : 0 |
No. of Tower Sites to be installed : 0 |
No. of Tower Sites to be installed : 0 |
No. of Tower Sites to be installed : 15 |
3 |
Upgradation of existing 19 Tower Sites for 2G mobile Services and installation of additional 18 New Mobile Tower Sites for provision of 4G mobile Services and creation of OFC Network for provision of FTTH in Lakshadweep islands by BSNL. |
Proposal finalised |
Proposal Approved, Work order placed to BSNL |
Tender done by BSNL for various works |
NIL (2G to 4G) NIL (4G New) NIL (OFC) |
4 |
Upgradation of existing 60 Tower Sites for 2G Mobile Services for provision of 4G Mobile Services in Andaman & Nicobar Islands by BSNL |
--- |
--- |
--- |
--- |
5 |
Deployment of Pilot Projects |
Approval by competent authority |
Rapid PoC |
Full deployment and certification testing |
Full deployment and certification testing |
6 |
Provision of Redundancy for Submarine Optical Fibre Connectivity for Andaman & Nicobar Islands by connecting Port Blair to Kolkata (Digha Beach) (CANI Project) |
Submission of DPR by TCIL Examination of DPR by USOF/DoT |
Approval and examination of DPR by competent authority |
Consultations with stakeholders and preparation of final proposal |
DCC and Cabinet Approval |
7 |
Provision of Submarine Optical Fibre Connectivity for Diglipur, Shaheed Dweep (Erstwhile Neil Island), Katchall, Teressa, Chowra, Nancowary and Little Nicobar Island under CANI Project as per request of Andaman & Nicobar UT Administration on turnkey basis to Indian Company to promote Atmanirbhar Bharat. |
Submission of DPR by TCIL Examination of DPR by USOF/DoT |
Approval and examination of DPR by competent authority |
Consultations with stakeholders and preparation of final proposal |
DCC and Cabinet Approval |
8 |
Provision of Last Mile connectivity at 5521 Satellite VSAT locations for installation of 9633 Wi-Fi Access Points |
Finalization tender and award of work by BBNL |
Tender failed |
Re-floating of tender |
No. of Wi-Fi APs to be provided: 100 |
9 |
Provision of Satellite VSAT Broadband Connectivity to balance GPs out of 4112 sites by BBNL under BharatNet (plus remaining GPs, if any, by BSNL/ BBNL) |
|
- |
Complete installation by Dec 2022 |
|
10 |
O&M of Satellite VSAT GPs/ DSPTs/ WiFi APs provided under BharatNet by BBNL/ BSNL as per SLA signed |
Continuous Monitoring |
|||
11 |
Redistribution of existing Satellite Bandwidth in Andaman & Nicobar Islands by BSNL for the Islands not connected on Submarine OFC as per request of ANI UT Administration |
Examination of DPR submitted by BSNL for vetting of Technical requirements and detailed cost estimates |
DPR examination by committee and clarifications from BSNL, UT ANI and MHA |
Award of work |
Completion |
12 |
Singapore cable & CLS |
Survey report |
DCC approval |
Cabinet approval |
Tender |
13 |
Lakshadweep Satellite Bandwidth |
No expansion required by UT LKD |
--- |
--- |
--- |
14 |
Telecom Technology Development Fund (TTDF) |
Preparation of Guidelines |
-Approval of DCC and Hon’ble MoC. -Launch of Scheme |
Receipt and Evaluation of proposals |
Approval and start of R&D projects |
15 |
Thai Com Satellite bandwidth |
Submission of proposal for approval |
--- |
--- |
Approval for migration of Thaicomm satellite VSATs on ISAT |
16 |
New Technologies for BharatNet |
|
|
Identification of new technologies for extending BharatNet |
Selection of suitable technologies |
17 |
Handing over of DSPTs to agencies of MHA/MoD |
|
|
Approval process |
Completion of the work |