1- The survey for 2,542 sites has been completed. As on 31.05.2026, 1,175 sites have been covered by installing 1,120 mobile towers in Andhra Pradesh, Bihar, Telangana, Jharkhand, Maharashtra, Chhattisgarh, Madhya Pradesh, Odisha, Uttar Pradesh and West Bengal. Implementation work is in progress. The project is likely to be completed by September 2026.
2- Additionally, 184 more locations have been added via various amendment to the scheme on the recommendation of MHA against the deleted location. The survey for 184 sites has been completed and as on 31.05.2026, 105 sites have been covered by installing 101 sites mobile towers. Implementation work is in progress. The roll out period of these additional sites is upto Oct, 2026.
| No of Orders | Executable Scope after survey | No. of sites commissioned | No. of location covered | |
|---|---|---|---|---|
| Sites | Locations | |||
| Sept-2021 Order | 1,269 | 1,329 | 1,120 | 1,175 |
| May-2023 Order | 79 | 82 | 74 | 77 |
| Sept-2023 Order | 21 | 23 | 18 | 19 |
| Oct-2023 Order | 8 | 8 | 7 | 7 |
| Mar-2024 Order | 10 | 10 | 2 | 2 |
| Aug-2025 order | 1 | 1 | ||
| Total | 1,388 | 1,453 | 1,221 | 1,280 |